How to quote a building job in South Africa
A building quote is a small contract. It has to define the scope against drawings, say who handles approvals, split the price into payments tied to stages, and set out how changes are priced. This guide works through a garage extension, with a staged payment schedule.
On this page: define the scope against something written · approvals and registrations · a worked example · tie payments to stages · variations · VAT · questions
Define the scope against something written
Quote from drawings, a measured sketch or a written specification, and say so on the quote. List what is in the price, such as foundations, brickwork, roof, plastering and finishes, and what is not: plans and professional fees, municipal and connection fees, landscaping and making good existing structures. Use a short list of assumptions ("soil conditions as visible", "existing slab level and sound") so a surprise below ground does not become a dispute.
Approvals and registrations
Check with the municipality whether building plan approval is needed for the work, and put on the quote who applies and who pays. If you build new homes, check whether registration and enrolment with the National Home Builders Registration Council (NHBRC) applies to you at nhbrc.org.za. Those rules depend on the type of job, so do not assume either way.
A worked example: a 20 square metre garage extension
| Item | Qty | Price | Total |
|---|---|---|---|
| Bricks and cement | materials | R9,500 | R9,500 |
| Builders: 2 builders for 6 days | 12 builder-days | R650 | R7,800 |
| Plumbing and electrical | allowance | R3,200 | R3,200 |
| Subtotal | R20,500 | ||
| VAT at 15% (if you are VAT-registered) | R3,075 | ||
| Total | R23,575 |
The example uses invented prices, to show the layout and the arithmetic. Use your own rates and costs. Anything priced as an allowance, such as the plumbing and electrical here, should say it is an allowance and what happens if the real cost is higher or lower.
Tie payments to stages
For a job of this size, one deposit and one final invoice leaves you funding the whole build. A common structure is a deposit followed by payments when each stage is finished. Using the example total of R23,575:
| Stage | Share | Amount including VAT |
|---|---|---|
| Deposit on acceptance | 30% | R7,072.50 |
| Foundations and floor slab complete | 30% | R7,072.50 |
| Walls and roof complete | 30% | R7,072.50 |
| Completion and handover | 10% | R2,357.50 |
These percentages are an example, not a rule. Agree them with the client, write them on the quote, and invoice each stage when it is reached. Some builders hold back a small retention until a snag list is cleared: if you do, state it.
Variations: changes after you start
Clients change their minds. Say on the quote that any change to the scope will be priced and agreed in writing before the work is done, and what the daily rate is for extra time. Send each variation as its own short quote so the client accepts it in writing: see can you charge more than your quote?
VAT
Add 15% only if you are VAT-registered, which is compulsory once your taxable supplies pass R2.3 million in 12 months. If you are not registered, the price you quote is the price, and the quote should say so. See whether you need to register.
Turn this into a quote in two minutes
Describe the job and your prices in plain words and Zuvo drafts the quote with line items and VAT in rand. Check it, send it, and the client can accept online.
Try Zuvo free for 14 days, no cardGeneral guidance with an illustrative example, not legal, technical or tax advice. Check approval, registration and contract requirements with your municipality, the NHBRC and an attorney for larger jobs. checked on 21 November 2026.
Questions people ask
What should a builder's quote include?
The scope against drawings or a written specification, materials and labour, allowances marked as allowances, what is excluded (plans, approvals, municipal fees, connections), the payment stages, how variations are handled, the start date and duration, VAT, and a valid-until date.
How should I split payments on a building job?
Tie them to stages: a deposit on acceptance, then payments as each stage such as foundations, walls and roof is complete, with a final payment at handover. The percentages are for you and the client to agree and write on the quote.
Do I need building plan approval before I quote?
It depends on the work and the municipality, so check with the municipality early and state on the quote who applies for approval and who pays.
Do I need to be registered with the NHBRC?
If you build new homes, check the NHBRC's rules on registration and enrolment, which depend on the type of work. The NHBRC website has the current requirements.
How do I handle changes after the quote is accepted?
Agree each change in writing, with a price, before doing it. Send it as a short variation quote that the client accepts, so the extra is on record.