A plumbing quote wins work when it is specific: the unit by capacity and type, labour on its own line, the Certificate of Compliance priced and named, and a clear list of what is not included. This guide uses a geyser replacement, the job most South African plumbers quote most often, with a worked example.
On this page: what to check on the visit · lines a plumbing quote needs · a worked example · certificate of Compliance · deposit and payment terms · when the job turns out bigger · VAT · questions
What to check on the visit
Quote after you have seen the job. For a geyser, look at:
- The existing unit: its capacity, whether it is electric, solar or a heat pump, and whether it is mounted in the ceiling or outside.
- Access: a tight ceiling hatch, a long carry, or a second floor changes the hours.
- The fittings around it: whether a drip tray, a pressure-control valve and isolation valve are present or have to be supplied.
- The pipework: old galvanised pipe that will not survive being disturbed is a risk to price in or exclude.
- The electrical side: the geyser's electrical connection is electrician's work, so say who is doing it.
The lines a plumbing quote needs
| Line | What to write |
|---|---|
| The unit | Capacity, type and brand, for example "150 litre electric geyser, [brand and model]". |
| Fittings | Drip tray, pressure-control valve, isolation valve and pipework, each included or not. |
| Labour | Hours at your rate, or a fixed price for the defined job, as its own line. |
| Call-out | A separate line if you charge one. |
| Old unit | Whether you remove and dispose of it. |
| Certificate of Compliance | Included or extra, what it costs, and who issues it. |
| Not included | Making good walls and ceilings, electrical work, tiling, and anything found once the old unit is out. |
A worked example: replacing a 150 litre geyser
| Item | Qty | Price | Total |
|---|---|---|---|
| Supply and install 150 litre geyser | 1 | R4,800 | R4,800 |
| Labour | 3 hrs | R450 | R1,350 |
| New pressure-control valve | 1 | R350 | R350 |
| Subtotal | R6,500 | ||
| VAT at 15% (if you are VAT-registered) | R975 | ||
| Total | R7,475 |
The example uses invented prices, to show the layout and the arithmetic. Use your own rates and costs. Under the table, write the terms: valid for 14 days, the exclusions from the list above, and the payment terms.
The Certificate of Compliance
A plumbing CoC from the Plumbing Industry Registration Board (PIRB) can only be issued by a PIRB Licensed Plumber, and whether the law requires one for a particular job depends on the work and the municipality. Homeowners often ask for one after a geyser job. Price it as its own line and name who will issue it, so the client is not surprised either way. Our homeowner guides explain what a CoC is and how clients check a plumber's PIRB registration, so put your registration number on the quote.
Deposit and payment terms
For a job that needs materials bought, a deposit covers the unit. A sensible term for the balance is on completion, or when you hand over the certificate. Put the terms on the quote, not only the invoice: see invoice payment terms.
When the job turns out bigger
Old pipework and rotten ceilings are found after the work starts. List "anything found once the old unit is out" as excluded, and agree any extra in writing, with a price, before you do it. Can you charge more than your quote? covers the rules.
VAT
Add 15% only if you are VAT-registered, which is compulsory once your taxable supplies pass R2.3 million in 12 months. If you are not registered, the price you quote is the price, and the quote should say so. See whether you need to register.
Turn this into a quote in two minutes
Describe the job and your prices in plain words and Zuvo drafts the quote with line items and VAT in rand. Check it, send it, and the client can accept online.
Try Zuvo free for 14 days, no cardGeneral guidance with an illustrative example, not legal, technical or tax advice. Registration and certificate points are from our verified guides on PIRB registration and certificates of compliance, checked on 15 November 2026. checked on 21 November 2026. Check what applies to your work and municipality.
Questions people ask
What should a plumbing quote include?
The plumber's name, business and registration number, the client and job address, the date and a valid-until date, the materials itemised (for a geyser, capacity, type and brand), labour on its own line, a call-out fee if any, whether the old unit is removed, the Certificate of Compliance, what is excluded, VAT, and the payment terms.
Should a plumbing quote include a Certificate of Compliance?
Say whether it is included and what it costs, and who issues it. A PIRB Certificate of Compliance can only be issued by a PIRB Licensed Plumber, and whether the law requires one depends on the job and the municipality.
Should I charge by the hour or a fixed price for plumbing?
A fixed price suits a defined job such as a geyser swap. Hourly suits fault-finding and repairs where you cannot know what you will find. Either way, show labour on its own line.
How long should a plumbing quote be valid?
Fourteen to thirty days is common, because material prices move. Put the date on the quote.
What should I leave out of a plumbing quote?
Say plainly what is excluded: making good walls and ceilings, tiling, electrical work to the geyser, and any extra work found once the old unit is out.