How to quote an electrical job in South Africa
An electrical quote has to settle three things the client cannot judge for themselves: what the existing installation needs before new work can be signed off, whether the Certificate of Compliance is included, and which parts are fixed price and which are hourly. This guide uses a lighting and distribution board job, with a worked example.
On this page: three kinds of electrical job, three ways to quote · what to check before you price · a worked example · certificate of Compliance · deposit and terms · VAT · questions
Three kinds of electrical job, three ways to quote
- New installation or alterations (new circuits, a new distribution board, downlights): quote a fixed price from a written scope, and include the test and certificate.
- Fault finding and repairs: you cannot know what you will find, so quote an hourly rate with a minimum, and say the quote will be updated once the fault is found.
- Compliance work for a sale: inspect first. The price depends on what the inspection finds, so quote the inspection and test, then the fixes.
What to check before you price
- The distribution board: its age, its capacity, whether there is space for new breakers, and the earth leakage protection.
- The existing wiring where the new work connects: damaged or non-compliant work may have to be corrected before you can certify yours.
- Access for cable runs, and whether ceilings or walls will need to be cut and made good.
- The materials that move in price: cable and breakers can change between the quote and the job, so keep the quote's validity short.
A worked example: downlights and a new distribution board
| Item | Qty | Price | Total |
|---|---|---|---|
| LED downlights, supplied and fitted | 12 | R180 | R2,160 |
| Distribution board, supplied and fitted | 1 | R2,400 | R2,400 |
| Labour | fixed | R3,600 | R3,600 |
| Certificate of Compliance and test report | 1 | R950 | R950 |
| Subtotal | R9,110 | ||
| VAT at 15% (if you are VAT-registered) | R1,366.50 | ||
| Total | R10,476.50 |
The example uses invented prices, to show the layout and the arithmetic. Use your own rates and costs. Below it, list what is excluded: making good ceilings and plaster, painting, and any repair to existing wiring that the inspection shows is needed before the new work can be certified.
The Certificate of Compliance
Under the Electrical Installation Regulations, 2009, a new installation may not be connected to the supply until it has been inspected and tested by a registered person and a Certificate of Compliance has been issued, and after an addition or alteration a new certificate is needed for at least that work. An owner may also not allow a change of ownership if the certificate is older than two years (regulation 7(5)). Quote the certificate and test report as their own line, and say who is the registered person signing it. Our homeowner guides explain the electrical CoC and how clients check an electrician, so include your registration details on the quote.
Deposit and terms
Take a deposit for the materials on any job larger than a call-out, and make the balance due when you hand over the certificate. Put it on the quote: see invoice payment terms.
VAT
Add 15% only if you are VAT-registered, which is compulsory once your taxable supplies pass R2.3 million in 12 months. If you are not registered, the price you quote is the price, and the quote should say so. See whether you need to register.
Turn this into a quote in two minutes
Describe the job and your prices in plain words and Zuvo drafts the quote with line items and VAT in rand. Check it, send it, and the client can accept online.
Try Zuvo free for 14 days, no cardGeneral guidance with an illustrative example, not legal, technical or tax advice. The certificate rules are from our verified guide to the Electrical Installation Regulations, 2009 (see what a CoC is), checked on 15 November 2026. checked on 21 November 2026. Check what applies to your work.
Questions people ask
What should an electrical quote include?
Your registration details, the client and address, a valid-until date, the materials itemised, labour, the Certificate of Compliance and test report as their own line, what is excluded (making good, painting, repairs to existing wiring), VAT, and the payment terms.
Should an electrician quote hourly or fixed price?
Fixed price suits new installations and alterations from a written scope. Hourly, with a minimum, suits fault finding and repairs where the problem is unknown until you open it up.
Does a Certificate of Compliance have to be on the quote?
It should be, as its own line, because the client needs to know it is included and who signs it. The Electrical Installation Regulations, 2009 require a certificate for new installations before connection and for additions and alterations.
How do I quote when I do not know what is behind the wall?
Quote the part you can see, state your assumptions, and say the price will be updated in writing if the work turns out to be larger. Agree any extra before you do it.
How long should an electrical quote be valid?
Keep it short, often 14 days, because cable and breaker prices change. Put the date on the quote.