Roofs are measured on the slope, not on the plan. A roof pitched at 30 degrees has about 15% more surface than the floor beneath it, so quoting from the house footprint under-prices the job. This guide measures a roof, works through a sheeting replacement, and covers the one thing that can change the whole quote: asbestos.

On this page: measure the slope, not the footprint · if the old roof may contain asbestos · what goes in the price · a worked example · VAT · questions

Measure the slope, not the footprint

The length of a roof slope is the horizontal run divided by the cosine of the pitch angle. For a simple gable roof over a house 8 m wide and 10 m long, pitched at 30 degrees, each side has a run of 4 m:

StepWorkingResult
Slope length of one side4 ÷ cos 30°4.62 m
Area of both sides2 × 4.62 × 1092.4 m²
Compare the footprint8 × 1080 m²

Add the overhang past the walls, and an allowance for overlaps and offcuts, which depends on the sheet profile. Measure hips, valleys, ridges and flashings by length, because they are priced by the metre.

If the old roof may contain asbestos

Do not quote an old cement-sheet roof as a normal strip and replace. Under the Asbestos Regulations, 2020 (Government Notice R. 1196 of 10 November 2020), removing asbestos cement products is classed as "type 2 asbestos work", which requires a registered asbestos contractor. The regulations treat removal of less than 10 square metres of asbestos cement products, where the work is not repeated on the same site within six months, as work that does not require registration. If you are not set up for asbestos work, quote the new roof and exclude removal, or bring in a registered contractor and say so. The gazette is on gov.za: read it for your job.

What goes in the price

A worked example: replacing 40 square metres of sheeting

Invented example: replace 40 square metres of roof sheeting on a house in Pretoria
ItemQtyPriceTotal
Roof sheeting40 m²R210R8,400
Roofers: 2 roofers for 3 days6 roofer-daysR600R3,600
New timber battenslump sumR1,400R1,400
SubtotalR13,400
VAT at 15% (if you are VAT-registered)R2,010
TotalR15,410

The example uses invented prices, to show the layout and the arithmetic. Use your own rates and costs. Add "rotten timber found once the sheeting is off" to the exclusions, with a rate for extra timber, so a hidden problem is priced in writing and not argued about afterwards.

VAT

Add 15% only if you are VAT-registered, which is compulsory once your taxable supplies pass R2.3 million in 12 months. If you are not registered, the price you quote is the price, and the quote should say so. See whether you need to register.

Turn this into a quote in two minutes

Describe the job and your prices in plain words and Zuvo drafts the quote with line items and VAT in rand. Check it, send it, and the client can accept online.

Try Zuvo free for 14 days, no card

General guidance with an illustrative example, not legal, technical or safety advice. The asbestos points are from the Asbestos Regulations, 2020 (Government Notice R. 1196), read on 21 November 2026. checked on 21 November 2026. Check the regulations and your insurance for your job.

Questions people ask

How do I measure a roof for a quote?

Measure on the slope: the horizontal run divided by the cosine of the pitch gives the slope length. In our example a 30 degree roof with a 4 m run has a slope of 4.62 m, so both sides of a 10 m long house are 92.4 m², more than the 80 m² footprint.

Can I remove an asbestos roof?

Under the Asbestos Regulations, 2020, removing asbestos cement products is type 2 asbestos work that requires a registered asbestos contractor, with a different rule for removal of less than 10 square metres that is not repeated on the same site within six months. Read the gazette for your job size, and exclude removal from your quote if you are not set up for it.

What should a roofing quote exclude?

Rotten timber found once the old roof is off, asbestos removal if you do not do it, gutters and fascias if not included, and delays caused by weather.

Should I quote roofing per square metre?

It is common for sheeting, but measure on the slope and list timber, flashings, ridge capping and labour separately so a hidden problem does not eat the margin.

How long should a roofing quote be valid?

Material prices move, so 14 to 30 days is common. Put the date on the quote.